The size of the “Cube”, by which the Courthouse is commonly referred, is well defined now with the structural steel in place and metal deck installation complete through Level 2.  The structure will continue to rise up through another nine levels and the roof to achieve the full “Cube” appearance. This progress through Level 2 has provided the required barrier for personnel safety at the lower levels and has permitted work to again move forward at the Basement Level.  The work at this Basement Level is concentrating on the construction of the concrete shear walls.  These walls are heavily reinforced concrete structures that will be a major focus on the project over the next seven months and will run in conjunction with the steel
erection that will continue in early August and extend to early 2015.  This project is being facilitated by Paul Crotty of Ventura Consulting Group.