“Our partnering goal was July 1 2013.  Contractually we had 220 working days. We probably used 165 days.  That isn’t the whole story though.  In 2011, we only worked 55 days, or so. Without partnering we probably would have worked 70 days this year.  The result of the community outreach that started as a result of partnering also enabled us to work longer hours every day.  At the end

Found some great info from the Calaveras Dam Replacement Project HERE!  The Calaveras Dam Replacement Project work site is a busy place on an average day. Machines both large and small are in constant motion, moving soils and materials from one side of the site to dispose of them on the other. However, this Wednesday around lunchtime was different. Work paused, for a short time, to celebrate the team’s achievement of